A very fast track, 35,000sq ft high quality fit out for international law firm, Ince & Co. Procured on a traditional 2 stage contract, the works took place on levels 14 and 15 of Aldgate Tower.

Following a soft strip out, the Cat B works included the installation of a new staircase with slab cut out, numerous meeting facilities,

a fully fitted kitchen, café, business lounge and bar. Bespoke joinery was used throughout along with back painted glass, stone, vinyl and carpet flooring, glazed partitioning and a combination of exposed ceilings, ceiling rafts and ceiling tiles.

  • Project

    Levels 14 & 15, Aldgate Tower

  • Value

    £4 million

  • Duration

    16 weeks

  • Project Manager

    Parker Wilson

  • Architect

    Aukett Swanke

  • QS

    Pierce Hill

  • Services Consultant

    Parker Wilson

Commercial Director

Chris Margiotta

Related Projects

Chris Margiotta

Commercial Director

Chris has recently joined Collins as Commercial Director, working in Duncan Redman's division.

Chris has worked as a Quantity Surveyor and Commercial Manager for 21 years, leading commercial teams on projects up to £250m. His strong experience in the education and residential sectors will support our growing portfolio of student accommodation schemes.

This website uses cookies to ensure the best possible experience for the user. Please accept or decline. See our cookie policy for more information