Project

60 Grove End Road, NW8 9NH

Value

£1.2 million

Duration

12 weeks

Architect

Sonnemann Toon Architects LLP

Structural Engineers

Symmetrys Ltd

This complete transformation of the St Francis Ward in The Hospital of St John and St Elizabeth involved the refurbishment of 15 en suite hospital bedrooms along with the reception and common areas. The design, created exclusively for their facility by Sonnemann Toon, was created to roll out on all future refurbishment projects. Collins presented a design that gave the rooms and bedheads a high-end look and feel. 

A new modern AC system was installed throughout the ward, and all en suites were clad in hygienic wall finishes and included bespoke HEWI sinks with IPS units. The reception was finished with Vanier and Corian in neutral colours giving it a bright and clean finish. After a successful handover, Collins are now on site on level 1 completing the refurbishment of the St Elizabeth’s ward, due to be handed over at the end of this year.