This complex project involved the strip out of all existing services, heavy structural demolition, new underground drainage and excavation works to this Grade II* listed building.

A steel roof including 110 glass panels was installed together with a new link area joining two buildings together.

New WC's and a shower core were created with all new services and a Cat B fit out including bespoke joinery, AV system, management suites, meeting rooms and a new restaurant. We had to keep 4 comms rooms live and maintain a fully operational book store with many original manuscripts safe for the duration of the works.

  • Project

    Senate House

  • Value

    £4.6m

  • Duration

    Phase 1 - 46 weeks, Phase 2 - 20 weeks

  • Project Manager

    Project Lab

  • Architect

    Space Lab

  • QS

    Project Lab

  • Services Consultant

    Energy Lab