• Project

    Smith Square, 77 Fulham Palace Road

  • Value

    £7 million

  • Duration

    52 weeks

  • Project Manager

    GIA

  • Architect

    TP Bennett

  • QS

    Hother Associates

  • Services Consultant

    John Brady Associates

A structural refurbishment at Smith Square for AXA Real Estate. The project involved extensive builders works and structural alterations. The 1st floor slabs were removed to form a two storey high space to create 5 new retail units, and two floors of new Cat A space.

We removed the existing brick fa├žade and installed a new glazed Stucco cladding system. With a new large two storey extension to the rear of the building, a new reception entrance to the building was formed along with a new external scenic lift from ground to 5th floor.