• Project

    City Place, Crawley

  • Value

    £6.5 million

  • Duration

    28 Weeks

  • Project Manager

    Paragon

  • Architect

    CBRE

  • QS

    Paragon

  • Services Consultant

    Hilson Moran

The complete refurbishment of 110,000 sq ft of office space over 4 floors, back to Cat A, followed by the fit out for Nestle of their new UK headquarters.

The new offices consist of open plan and cellurised office space, comms room, meeting rooms, auditorium, gymnasium and changing rooms, professional kitchen and dining area.

A “right first time” attitude allowed Cisco to fit out the Telepresence Room after a complex IT/AV installation by Collins. Early handover of the comms room enabled the client to prepare for the arrival of 800 plus staff in a seamless operation.